What are the two major sections of planning for a self-erecting tower crane?

Prepare for the NCCCO Tower Crane Operator Test. Study with flashcards and multiple-choice questions, complete with hints and explanations. Get ready to ace your exam!

The correct choice highlights the comprehensive aspects involved in planning for a self-erecting tower crane, which includes Delivery, Set Up, Erection and Dismantle, and Lifting Operations. Each of these components plays a crucial role in ensuring the safe and efficient operation of the crane.

Delivery involves getting the crane to the job site and handling logistics associated with transportation. This phase ensures that all equipment arrives in good condition and is ready for assembly.

Set Up refers to the initial assembly of the crane and preparing it for use. This includes ensuring the crane is positioned correctly, securely on stable ground, and that all assembly procedures are followed to adhere to safety standards.

Erection refers to the actual process of raising the crane to its operational height, which is critical for its functionality and involves precise procedures to avoid accidents.

Dismantle is the reverse of the erection process and consists of safely taking down the crane once the project is completed. Planning this phase is vital for maintaining safety and efficiency.

Lifting Operations encompass the actual use of the crane for its intended lifting tasks, including load management, communication, and adherence to safety protocols while operating the crane.

By addressing all of these elements together, the planning process ensures that the crane operates effectively throughout